DC 차단 스위치를 설치하는 방법: NEC 호환 배선

소개

DC 차단 스위치 installation requires meticulous attention to location selection, proper grounding, correct wire sizing, torque specifications, and comprehensive labeling to ensure 25-30 years of safe, code-compliant operation. Unlike plug-and-play AC electrical work, DC disconnect installation involves unique challenges: sustained arc risks demanding proper contact alignment, high voltage (up to 1500V DC) requiring enhanced clearances, and life-safety implications where incorrect installation creates shock hazards during maintenance operations.

This professional installation guide provides step-by-step procedures for installing DC disconnect switches in photovoltaic systems. We cover site selection meeting NEC accessibility requirements, mounting techniques for various enclosure types, wire sizing methodology accounting for voltage drop and temperature derating, proper termination procedures including torque specifications, grounding and bonding requirements, code-compliant labeling, and comprehensive pre-energization testing procedures.

For solar installers, electrical contractors, and technical personnel performing disconnect installations, this guide ensures first-time-right work that passes inspection, operates reliably, and protects system personnel as designed throughout project lifespans.

💡 Installation Priority: Proper location and labeling prevent 70% of disconnect-related safety issues. A perfectly wired disconnect installed in an inaccessible location or without proper warning labels fails its safety mission—technicians and emergency responders must immediately identify and access disconnects during emergencies.

Pre-Installation Planning and Site Selection

NEC 690.13-690.17 Location Requirements

Building Disconnect Location (NEC 690.13):

“Readily Accessible” Definition (NEC Article 100):
– Reachable quickly without climbing over/removing obstacles
– No ladders required
– No locked doors (unless serving equipment in that room)
– Not in concealed locations (behind panels, above ceilings)

Specific Requirements:
– Mounting height: 3.5 to 6.5 feet above finished grade/floor
– Distance from building entry: Within sight OR marked with permanent directory
– Clear working space: 3 feet × 30 inches minimum (NEC 110.26)
– Illumination: Adequate lighting for safe operation (200 lux minimum at disconnect)
– Weather protection: If outdoor, NEMA 3R minimum enclosure

Equipment Disconnect Location (NEC 690.15):

Within Sight Requirement:
– Distance: Maximum 50 feet AND visible from equipment
– Test: Standing at equipment, can you see the disconnect without moving? If yes = within sight
– Alternative: Remote disconnect MUST be lockable in open position if not within sight

Example Compliant Locations:

Good Location 1: Exterior wall next to utility meter
– Height: 5 feet above grade
– Clear space: 3 feet in front of disconnect
– Marked with weatherproof label: “PHOTOVOLTAIC SYSTEM DISCONNECT”
– Visible from street (emergency access)

Good Location 2: Interior garage wall near main panel
– Height: 4.5 feet from floor
– Illumination: Garage lighting provides adequate visibility
– Clear access: No vehicles or storage blocking
– Within sight of main breaker panel

Poor Location 1: On roof next to array
– Requires ladder to access (NOT readily accessible)
– Emergency personnel cannot safely reach
– Violates NEC 690.13

Poor Location 2: Inside locked electrical room
– Locked doors prevent emergency access
– Only acceptable if disconnect serves equipment inside that room
– Building disconnect must be outside locked areas

Site Assessment Checklist

Before purchasing or installing disconnect, verify:

Structural Considerations:
– [ ] Mounting surface can support disconnect weight + wire weight
– Small enclosed switch (30-60A): 10-20 lbs
– Large enclosed switch (200-400A): 30-60 lbs
– Disconnect combiner box: 40-100 lbs loaded
– [ ] Wall construction adequate: Masonry, concrete, plywood ≥ 3/4″, or metal studs with backing plate
– [ ] Surface is flat within 1/4″ over disconnect footprint
– [ ] No obstructions behind mounting location (check for existing wiring, plumbing, HVAC)

Environmental Factors:
– [ ] Sun exposure: Direct sun can heat enclosure to 70-80°C, requiring NEMA 3R+ and temperature derating
– [ ] Rain/snow exposure: Outdoor locations require NEMA 3R minimum (rain-tight)
– [ ] Wind load: Coastal/high-wind areas need additional mounting anchors
– [ ] Salt spray exposure: Coastal locations within 1 mile of ocean require NEMA 4X stainless steel
– [ ] Temperature extremes: If installed location experiences -40°C to +70°C, verify disconnect rated for temperature range

Accessibility Verification:
– [ ] 3-foot working clearance in front of disconnect (measure from door swing when open)
– [ ] 30-inch width clearance (centered on disconnect)
– [ ] 6.5-foot height clearance above working space
– [ ] No storage, equipment, or landscaping in working clearance zone
– [ ] Path to disconnect unobstructed (no gates, doors, or barriers requiring keys)

Conduit and Wiring Access:
– [ ] Conduit entry locations suitable (top, bottom, sides per disconnect design)
– [ ] Minimum bending radius for conduit can be achieved: 6× conduit diameter for rigid, 10× for EMT
– [ ] Sufficient space for wire termination inside enclosure (large conductors require significant bending room)
– [ ] Grounding electrode accessible if required for new grounding system

Wire Sizing and Preparation for DC Disconnect

NEC-Compliant Conductor Sizing

Formula (NEC 690.8, 690.17):

Wire ampacity (after derating) ≥ 125% of maximum circuit current

Step-by-Step Calculation:

Step 1 – Determine Maximum Circuit Current:

I_max = I_sc × 1.25 (high irradiance factor)

Step 2 – Calculate Minimum Conductor Ampacity:

I_conductor = I_max × 1.25 (continuous operation factor)
= I_sc × 1.56

Step 3 – Apply Temperature Correction:

If conductors in high-temperature environment:

I_conductor_derated = I_conductor / k_temp

Where k_temp from NEC Table 310.15(B)(2)(a):

주변 온도Correction Factor (75°C insulation)
30°C (86°F)1.00
40°C (104°F)0.88
50°C (122°F)0.75
60°C (140°F)0.58

Step 4 – Apply Conduit Fill Adjustment (NEC 310.15(B)(3)(a)):

If >3 current-carrying conductors in conduit:

Number of ConductorsAdjustment Factor
1-31.00 (no adjustment)
4-60.80
7-90.70

Complete Example:

시스템: 8 parallel strings combined, feeding through disconnect to inverter
– Combined I_sc: 8 × 11A = 88A
– Conductors run in outdoor conduit on sunny wall: 60°C expected
– Two current-carrying conductors (DC+ and DC-)

Calculation:
– I_max = 88A × 1.25 = 110A
– I_conductor = 110A × 1.25 = 137.5A
– Temperature derating: k_temp = 0.58 (60°C)
– Conduit fill: k_fill = 1.00 (only 2 conductors)
– Required ampacity at 30°C: I_conductor_30C = 137.5A / (0.58 × 1.00) = 237.1A

From NEC Table 310.16 (75°C copper THWN-2):
– 2 AWG: 115A (insufficient)
– 1 AWG: 130A (insufficient)
– 1/0 AWG: 150A (insufficient)
– 2/0 AWG: 175A (insufficient)
– 3/0 AWG: 200A (insufficient)
– 4/0 AWG: 230A (insufficient)
– 250 kcmil: 255A ✓

Selected: 250 kcmil copper THWN-2

⚠️ Critical Mistake: Many installers select wire based on disconnect rating (e.g., “200A disconnect = use wire rated 200A at 30°C”). This ignores temperature derating and can result in dangerously undersized conductors. Always calculate from source current with all derating factors applied.

Wire Stripping and Terminal Installation

Proper Stripping Technique:

For Compression Lugs (Large Conductors ≥ 2 AWG):
1. Measure lug barrel length: typically 1.5-2.5 inches
2. Strip insulation to expose conductor matching barrel length
3. Use cable stripper or utility knife (careful not to nick conductors)
4. Inspect for nicked strands: If >5% of strands damaged, cut off and re-strip
5. Apply antioxidant compound for aluminum conductors (not needed for copper in indoor applications)

For Ring Terminals (Small Conductors ≤ 4 AWG):
1. Strip 3/4 inch (typical for screw terminals)
2. Twist stranded conductors clockwise to tighten
3. Insert into ring terminal barrel until conductor visible through inspection hole
4. Crimp using appropriate die (match terminal color coding):
– Red: 22-18 AWG
– Blue: 16-14 AWG
– Yellow: 12-10 AWG
5. Apply heat shrink tubing over barrel for additional insulation
6. Pull-test: 20-30 lb force, no slippage

Compression Lug Installation:

For Large Conductors (1/0 AWG and larger):

Tools required:
– Hydraulic crimper or battery-powered compression tool
– Correct die set for lug size
– Torque wrench for terminal bolts

Procedure:
1. Select lug matching conductor size (marked on lug body)
2. Strip conductor to lug barrel length
3. Insert conductor fully into barrel (bottom out against lug stop)
4. Position compression die over hex section of barrel (not on conductor!)
5. Compress until die releases (hydraulic crimper) or indicator shows complete (ratcheting crimper)
6. Tug-test: Apply 50-100 lb force, no movement
7. Visually inspect: Compression marks should be uniform around barrel

Terminal Bolt Installation:
1. Place compression lug over disconnect terminal stud
2. Install flat washer (if provided with disconnect)
3. Install lock washer or split-bolt locknut
4. Hand-tighten nut until snug
5. Final torque with torque wrench (see torque specifications below)

DC disconnect switch wire termination showing proper compression lug installation torque wrench application and ring terminal crimping for photovoltaic system wiring quality

Mounting and Physical Installation Procedures

Surface Mount Installation (Most Common)

Step 1 – Layout and Marking:

1. Position disconnect at desired location (verify height 3.5-6.5 feet)
2. Use level to ensure enclosure is plumb (vertical) and level (horizontal)
3. Mark mounting hole locations through enclosure back or using template
4. For large/heavy enclosures: Use helper or temporary support to hold position while marking

Mounting Hole Pattern Considerations:
– Small enclosed switches (30-60A): 4 corner mounting holes typical
– Large enclosed switches (200-400A): 6-8 mounting holes (additional at mid-points)
– Combiner boxes: 8-12 mounting holes depending on size

Step 2 – Drilling and Anchor Installation:

For Wood Mounting Surface (Plywood, OSB, wood studs):
– Drill pilot holes: diameter = 80% of screw shank diameter
– Use wood screws: #10 or #14, length ≥ 1.5 inches into solid wood
– Torque: 15-25 lb-in (hand screwdriver firm, not impact driver)

For Masonry/Concrete Surface:
– Drill holes with hammer drill and masonry bit
– Hole diameter: Match anchor size (typically 3/8″ for light enclosures, 1/2″ for heavy)
– Depth: Anchor length + 1/2 inch
– Install expansion anchors or Tapcon screws
– Torque: 25-40 lb-in (do not overtighten—can crack concrete or strip anchor)

For Metal Siding/Thin Wall:
– Use backing plate or locate wall studs
– Toggle bolts or molly bolts for hollow walls
– Minimum pull-out strength: 200 lbs for small enclosures, 500 lbs for large

Step 3 – Enclosure Mounting:

1. Lift enclosure into position (use helper for >30 lb enclosures)
2. Insert top mounting screws first, tighten partially (allows adjustment)
3. Verify level, adjust if needed
4. Install remaining screws
5. Final torque all mounting screws to specification
6. Pull-test: Enclosure should not move when pulled with moderate force

Step 4 – Weatherproofing (Outdoor Installations):

– Apply silicone caulk around perimeter between enclosure and wall
– Leave bottom edge unsealed (allows condensation drainage if any moisture enters)
– Install rain shield above enclosure if exposed to direct rain (optional but recommended)

Post/Pole Mount Installation (Ground Arrays)

Post Installation:

For Permanent Installation:
1. Dig hole: 36 inches deep, 12 inches diameter
2. Install 4×4 inch treated lumber or 3-inch steel pipe
3. Pour concrete: 3000 psi minimum, fill hole, allow 48 hours cure
4. Post height above grade: 4-5 feet (positions disconnect at 5-6 feet center height)

For Temporary/Portable (Trade show displays, test installations):
1. Use weighted base: 50-100 lb concrete-filled base plate
2. Post clamps to secure to existing structures
3. Ground mount pad with anchors

Enclosure Mounting to Post:

Wood Post:
– Use lag screws: 3/8 inch × 3 inches, 4-6 screws depending on enclosure size
– Pre-drill: 1/4 inch diameter pilot holes
– Torque: 25-35 lb-in

Steel Post/Pipe:
– Use U-bolts matching pipe diameter
– Two U-bolts minimum (top and bottom of enclosure)
– Torque: 30-45 lb-in (alternate tightening each side to prevent bending)

Conduit Routing:
– Run conduit down post interior (if hollow) or alongside exterior
– Underground conduit: 18 inches minimum burial depth for rigid, 24 inches for PVC (NEC 300.5)
– Transition from underground to post: Use LB conduit body or sweep elbow
– Seal all openings: Prevent water entry into post

Termination Procedures and Torque Specifications

Terminal Identification and Wiring

Disconnect Terminal Markings:

Input/Line Side (Array):
– Marked: “LINE”, “INPUT”, or “SOURCE”
– Positive terminal: Usually red marking or “+” symbol
– Negative terminal: Usually black marking or “-” symbol
– Connects to: PV array (through combiner box if present)

Output/Load Side (Inverter):
– Marked: “LOAD”, “OUTPUT”, or equipment being powered
– Positive terminal: Red or “+”
– Negative terminal: Black or “-“
– Connects to: Inverter DC input terminals

Ground Terminal:
– Marked: “GND”, green screw, or ground symbol
– Typically on enclosure interior, may be separate lug or ground bar
– Connects to: Equipment grounding conductor (green or bare copper)

Wiring Sequence:

Correct Order (minimizes risk):
1. Ground first: Connect equipment grounding conductor to ground terminal
2. Negative second: Connect DC- (negative) conductor to negative terminals
3. Positive last: Connect DC+ (positive) conductor to positive terminals

Rationale: If accidental contact occurs during wiring, grounded tools/enclosure provide fault path. Positive is most hazardous (highest voltage to ground in most systems), so connected last.

Torque Specifications by Terminal Type

Terminal TypeWire Size RangeTorque SpecificationTool Required
Screw Terminal (Small Disconnect)14-10 AWG20-30 lb-in
(2.3-3.4 Nm)
Torque screwdriver
Lug Terminal (Medium Disconnect)8-2 AWG35-50 lb-in
(4.0-5.6 Nm)
Torque wrench
Lug Terminal (Large Disconnect)1/0-250 kcmil50-75 lb-in
(5.6-8.5 Nm)
Torque wrench
Bus Bar Stud (Combiner)300-750 kcmil75-150 lb-in
(8.5-17 Nm)
Torque wrench
Ground TerminalPer NEC 250.12235-50 lb-in
(4.0-5.6 Nm)
Torque wrench

Torque Application Best Practices:

1. Set torque value on wrench per table above
2. Insert socket or bit squarely onto fastener
3. Apply steady pressure increasing gradually
4. Stop immediately when wrench “clicks” or releases
5. Do NOT continue turning after click (over-torque damages threads)
6. Re-torque after 10-15 minutes: Terminals “settle”, retorque brings back to spec
7. Mark torqued connections: Small paint dot or torque indicator shows work completed

Under-Torque Consequences:
– High contact resistance (I²R heating)
– Terminal temperature can reach 80-150°C
– Insulation melting
– Connection failure (arcing)
– 60% of connection failures caused by under-torque

Over-Torque Consequences:
– Stripped threads (terminal unusable)
– Cracked terminal blocks
– Crushed compression lugs (reduced contact area)
– Broken fasteners
– 10% of connection failures caused by over-torque

🎯 Field Practice: If torque wrench unavailable (emergency field repair), “firm hand-tight” with insulated screwdriver ≈ 25-30 lb-in for small terminals. However, ALWAYS use calibrated torque tools for initial installation and scheduled maintenance.

Grounding and Bonding Requirements

Equipment Grounding Conductor Sizing

NEC 250.122: Equipment grounding conductor sized per overcurrent device rating.

Overcurrent Device RatingCopper EGC SizeAluminum EGC Size
15-20A14 AWG12 AWG
30A10 AWG8 AWG
60A10 AWG8 AWG
100A8 AWG6 AWG
200A6 AWG4 AWG
400A3 AWG1 AWG

:
– Disconnect: 200A rating
– Overcurrent protection: 200A fuse upstream
– Required EGC: 6 AWG copper minimum

설치:
1. Route EGC in same conduit as DC+ and DC- conductors (NEC 250.134)
2. Terminate at disconnect ground terminal or ground bus
3. Bond disconnect enclosure to EGC (required per NEC 250.86)
4. Verify continuity: Enclosure to ground terminal < 0.1Ω

Grounding Electrode System Connection

When Required (NEC 250.52, 690.47):

Grounding electrode system connection required if:
– PV system is at separate building from main service
– PV array located >50 feet from main building
– System operates at >50V to ground

Grounding Electrode Types (NEC 250.52):

Preferred Electrodes:
1. Ground rod: 8 feet × 5/8 inch diameter minimum, copper-clad steel
2. Ground plate: 2 feet² area buried, 0.06 inch thick copper
3. Ground ring: #2 AWG bare copper, 20 feet minimum length, buried 2.5 feet

Installation Procedure – Ground Rod:

1. Drive rod: 8-foot ground rod, only 6 inches max above grade after driving
2. If bedrock encountered: Drive at 45° angle OR bury horizontally in 2.5-foot trench
3. Test resistance: Use ground resistance tester
4. Target: <25Ω (NEC 250.53) 5. If >25Ω: Install second rod at least 6 feet from first
6. Bond rods: #6 AWG copper minimum

Grounding Electrode Conductor (GEC) Sizing:

Per NEC 250.66, based on largest ungrounded conductor:

Largest Ungrounded ConductorGEC Size (Copper)
2 AWG or smaller8 AWG
1 AWG or 1/0 AWG6 AWG
2/0 or 3/0 AWG4 AWG
4/0-350 kcmil2 AWG
Over 350 kcmil1/0 AWG

Connection Method:
– Use listed ground rod clamp (bronze or brass, UL listed)
– Irreversible compression connector (preferred for permanent)
– Exothermic welding (Cadweld) for high-reliability applications

라벨링 및 표시 요건

NEC 690.56: Photovoltaic System Identification

Required Labels for DC Disconnect:

Primary Label – PV System Disconnect:

Text (minimum):

PHOTOVOLTAIC SYSTEM DISCONNECT

DANGER HIGH VOLTAGE DC Nominal System Voltage: 800V DC Maximum System Voltage: 920V DC Short-Circuit Current: 88A Available Fault Current: 180A

Date of Calculation: 10/2025

Specifications:
– Material: Reflective, weather-resistant, UV-stable
– Text: Black on yellow background (ANSI Z535.4)
– Minimum text height: 3/8 inch for primary words
– Mounting: Permanent adhesive or mechanical fasteners
– Location: Front of disconnect enclosure, readily visible

Arc Flash Warning Label (NFPA 70E):

WARNING
ARC FLASH AND SHOCK HAZARD

Appropriate PPE Required Arc Flash Boundary: 4 feet PPE Category: 2 Incident Energy: 4.2 cal/cm²

AUTHORIZED PERSONNEL ONLY

Directional Labels:

LINE (Array) Side:
– Label both terminals: “LINE – ARRAY”
– Or: “INPUT FROM PV ARRAY”
– Include polarity: “+” and “-” symbols

LOAD (Inverter) Side:
– Label both terminals: “LOAD – INVERTER”
– Or: “OUTPUT TO EQUIPMENT”
– Include polarity: “+” and “-” symbols

Additional Required Markings

Operating Instructions (if not obvious):

OPERATING INSTRUCTIONS

TO DISCONNECT: 1. Rotate handle counterclockwise to OFF 2. Verify visible break through window 3. Test for voltage (should read 0V) 4. Apply lockout device if performing maintenance

TO RECONNECT: 1. Remove lockout device 2. Verify no personnel downstream 3. Rotate handle clockwise to ON 4. Verify system operation normal

Rapid Shutdown Markings (NEC 690.12, if applicable):

If system includes rapid shutdown:

PHOTOVOLTAIC SYSTEM EQUIPPED WITH
RAPID SHUTDOWN
Operates per NEC 690.12
Conductors reduce to ≤80V within 10 seconds

Equipment Data Plate:

Disconnect manufacturer data plate must remain visible and include:
– Manufacturer name
– Model number
– Voltage rating (DC)
– Current rating
– Short-circuit rating (if applicable)
– UL listing mark or equivalent
– Temperature rating

🎯 Inspector Tip: During inspection, inspector will verify (1) Disconnect is DC-rated for system voltage, (2) All required labels present and legible, (3) LINE/LOAD marked correctly (polarity not reversed). Pre-check these three items before requesting inspection to avoid re-inspection delays.

DC disconnect switch showing NEC-compliant labeling including photovoltaic system identification arc flash warning and directional LINE-LOAD markings for code compliance and safety

테스트 및 커미셔닝 절차

Pre-Energization Testing Sequence

Test 1 – Visual Inspection Checklist:

– [ ] All terminals torqued to specification
– [ ] No loose wire strands outside terminals
– [ ] Wire labels match drawings (LINE, LOAD, polarity)
– [ ] Enclosure mounting secure (pull-test confirms)
– [ ] All conduit entries sealed (maintain NEMA rating)
– [ ] Ground terminal bonded to enclosure
– [ ] Labels installed and legible
– [ ] Disconnect operates smoothly (no binding)
– [ ] Visible break window clean and unobstructed

Test 2 – Continuity Testing:

Purpose: Verify complete circuit when disconnect closed

Procedure:
1. Ensure disconnect in CLOSED position
2. Set multimeter to resistance (Ω) mode
3. Measure LINE positive to LOAD positive: Should read <0.01Ω 4. Measure LINE negative to LOAD negative: Should read <0.01Ω 5. Measure LINE to LOAD (opposite polarities): Should read infinite (open circuit) Interpretation:
– Reading 0.00-0.01Ω: Excellent connection ✓
– Reading 0.01-0.10Ω: Acceptable but check torque
– Reading >0.10Ω: Poor connection, likely under-torqued terminal
– Reading infinite (OL) on same polarity: Disconnect not fully closed or internal failure

Test 3 – Insulation Resistance (Megohm) Testing:

Equipment: Insulation resistance tester (megohmmeter), 500V or 1000V test voltage

Purpose: Verify no insulation faults before energization (prevents ground faults and shock hazards)

Procedure:

Test 3A – LINE to Ground:
1. Disconnect in OPEN position
2. Connect megohmmeter positive lead to LINE positive terminal
3. Connect megohmmeter negative lead to enclosure ground terminal
4. Apply 500V DC test for 1 minute
5. Read insulation resistance
6. Pass: >1.0 MΩ (NEC 690.5 minimum)
7. 우수: >10 MΩ
8. Repeat for LINE negative to ground

Test 3B – LOAD to Ground:
1. Same procedure as Test 3A, but measure LOAD side terminals
2. Verifies downstream equipment insulation adequate

Test 3C – LINE to LOAD (across open disconnect):
1. Disconnect in OPEN position
2. Measure LINE positive to LOAD positive
3. Should read >10 MΩ (verifies contacts truly open)

Common Failure Modes:
– Reading 0.1-1.0 MΩ: Moisture in connections, allow drying and re-test
– Reading <0.1 MΩ: Ground fault present, inspect all connections for damage – Reading decreasing during test: Active leakage, indicates compromised insulation Test 4 – Polarity Verification:

Purpose: Ensure LINE/LOAD and +/- correctly identified (prevents equipment damage)

Procedure:
1. Disconnect in OPEN position
2. Energize array (uncover modules if covered)
3. Measure LINE side:
– LINE positive to ground: Should read +V_oc (e.g., +800V in ungrounded system)
– LINE negative to ground: Should read -V_oc or 0V (depending on grounding)
– LINE positive to LINE negative: Should read full V_oc (800V)
4. Verify polarity markings match actual voltage polarity
5. LOAD side should read 0V (disconnect open, no connection)

If Polarity Reversed:
– DO NOT close disconnect (can damage inverter)
– Correct wiring before proceeding
– Re-label as needed

에너지화 및 부하 테스트

Energization Procedure:

Step 1 – Initial Energization:
1. Verify all tests passed
2. Ensure no personnel downstream (communication with team)
3. Close disconnect (rotate handle to ON)
4. Observe for: Arcing (should be none), unusual sounds, visible smoke
5. If any abnormality: Immediately open disconnect and investigate

Step 2 – Voltage Verification:
1. Measure LOAD side voltage (disconnect closed):
– LOAD positive to negative: Should equal LINE voltage (e.g., 800V)
– Voltage drop across disconnect: <0.5V (0.06% typical) 2. If voltage drop >2V: Check terminal torque, verify contacts clean

Step 3 – Load Current Testing:
1. Connect inverter (or test load)
2. Inverter begins normal operation
3. Measure current at disconnect output (clamp meter around conductor)
4. Expected: Near inverter rated DC input current (varies with irradiance)
5. Verify current balanced between positive and negative (should be equal within 2%)

Step 4 – Operational Cycling Test:
1. Open disconnect (system de-energizes)
2. Verify visible break (look through window, see air gap)
3. Measure LOAD voltage: Should drop to 0V within 1 second
4. Close disconnect (system re-energizes)
5. Measure LOAD voltage: Should restore to full V_oc within 1 second
6. Repeat cycle 3-5 times to verify consistent operation

Step 5 – Thermal Inspection:
1. Allow system to operate at >50% load for 30 minutes minimum
2. Use infrared thermometer or camera
3. Scan all terminals (LINE and LOAD, positive and negative)
4. Expected temperature rise: <30°C above ambient 5. Hot spots (>50°C above ambient) indicate problems:
– Under-torqued terminal: Re-torque immediately
– Oversized conductor for terminal: Verify proper size range
– Internal disconnect contact issue: Contact manufacturer

Acceptance Criteria:
– [ ] No arcing or sparking during operation
– [ ] Voltage drop across disconnect <2% – [ ] No terminal temperature rise >30°C above ambient
– [ ] Visible break confirmed when opened
– [ ] Smooth operation (no binding or excessive force required)
– [ ] All labels present and correct

Common Installation Mistakes and Corrections

Mistake #1: Undersized Wire for Temperature Environment

Problem:
Installer selects 2 AWG wire for 200A disconnect based on 115A ampacity at 30°C, ignoring that disconnect is mounted on sunny exterior wall reaching 60°C.

Consequence:
– Wire ampacity at 60°C: 115A × 0.58 = 66.7A
– System actual current: 137.5A (from I_sc × 1.56 calculation)
– Wire severely undersized: overheats, insulation melts, fire risk

Correction:
– Calculate from source current with temperature derating applied
– Required: 137.5A / 0.58 = 237.1A at 30°C
– Selected: 250 kcmil copper (255A at 30°C) ✓
– Or: Relocate disconnect to shaded location and use properly-sized wire for cooler environment

Prevention: Always determine disconnect mounting location and expected ambient temperature BEFORE sizing wire. Document temperature assumption in design calculations.

Mistake #2: Reversed LINE/LOAD Connections

Problem:
Installer connects array to LOAD terminals, inverter to LINE terminals (backwards).

Consequence:
– During normal operation: System appears to function (voltage present, current flows)
– During maintenance: Opening disconnect does NOT isolate inverter
– Technician believes system isolated (disconnect open), but inverter still energized from array through backwards wiring
– Shock hazard—defeats entire purpose of disconnect

Correction:
– Verify LINE terminals connected to upstream source (array)
– Verify LOAD terminals connected to downstream equipment (inverter)
– Use voltage testing: With disconnect OPEN, LINE side should have voltage, LOAD side should be 0V

Prevention:
– Label conductors at BOTH ends before installation: “ARRAY – LINE”, “INVERTER – LOAD”
– Follow color coding: Use consistent wire colors for LINE vs LOAD
– Test polarity after installation before commissioning

Mistake #3: Inadequate Grounding Conductor

Problem:
Installer uses 10 AWG copper equipment grounding conductor for 200A disconnect (should be 6 AWG per NEC 250.122).

Consequence:
– Ground fault current path has excessive resistance
– During fault: Voltage rise on enclosure can reach 50-150V (dangerous touch potential)
– Overcurrent device may not trip quickly enough
– Personnel shock hazard

Correction:
– Replace 10 AWG with 6 AWG copper EGC
– Verify NEC Table 250.122 for correct size based on overcurrent device rating (not conductor size!)
– Test ground fault path: Inject test current, measure enclosure voltage rise

Prevention: Size EGC per overcurrent device rating, NOT per conductor size. Common mistake: “I used 2 AWG for power, so 10 AWG ground is fine”—NO, must use Table 250.122.

Mistake #4: Missing or Incorrect Labels

Problem:
Disconnect installed with generic handwritten label “Solar Disconnect” and no voltage/current ratings.

Consequence:
– Code violation (NEC 690.56 requires specific information)
– Emergency responders don’t know voltage level (300V? 800V? 1500V?)
– Maintenance personnel unaware of hazards
– Inspection failure

Correction:
– Install compliant label with all required information:
– “PHOTOVOLTAIC SYSTEM DISCONNECT”
– Nominal and maximum voltage
– Short-circuit current
– Available fault current
– Date of calculation
– Use professional pre-printed labels or label maker
– Permanent materials (reflective, UV-stable, adhesive or mechanical mount)

Prevention: Order required labels with disconnect or before installation. Template labels with system-specific data to be filled in during commissioning.

Mistake #5: Over-Torquing Terminals

Problem:
Installer uses impact driver to tighten disconnect terminals, applying ~200 lb-in torque (specification is 50 lb-in).

Consequence:
– Stripped threads in terminal block (unrepairable)
– Cracked terminal housing
– Crushed compression lugs (reduced contact area → heating)
– Disconnect must be replaced ($300-500 cost + labor)

Correction:
– Use calibrated torque wrench for all terminal connections
– Set torque per manufacturer specification (typically 35-75 lb-in)
– Stop immediately when wrench clicks
– Never use impact drivers on electrical terminals

Prevention: Include torque wrench in tool kit, verify calibration annually. Train installers on proper torque technique. Witness first installation of new technicians to verify procedures correct.

자주 묻는 질문

What size wire do I need for a 200A DC disconnect switch?

Wire size must be calculated from SOURCE current, not disconnect rating, accounting for temperature derating. Formula: I_wire = (I_sc × 1.56) / k_temp where k_temp is temperature correction factor for ambient conditions. Example: array I_sc = 88A, disconnect in 60°C location gives I_wire = (88A × 1.56) / 0.58 = 237A required at 30°C, requiring 250 kcmil copper (255A rating). Common mistake: selecting wire just to match disconnect rating ignores NEC 690.8 source-based sizing and temperature derating per NEC 310.15(B)(2)(a). Disconnect rating is maximum the switch can handle—wire must be sized for ACTUAL system current after all factors applied. Under-sized wire overheats before disconnect trips, creating fire hazard. Always size from source current with temperature derating per actual installation environment, not disconnect nameplate rating.

Where should I mount the solar disconnect switch?

NEC 690.13 requires “readily accessible” location: mounting height 3.5-6.5 feet above grade, reachable quickly without ladders or climbing, not behind locked doors (unless serving equipment in locked room), with 3-foot clear working space in front. Building disconnect goes at point where PV conductors enter building OR readily accessible location outside. Equipment disconnect must be within sight of inverter (50 feet maximum AND visible from equipment) OR remote but lockable in open position. Outdoor installations require NEMA 3R minimum weatherproof enclosure. Poor locations: rooftop (requires ladder access), locked rooms, concealed locations (behind panels), basement corners with storage blocking access. Emergency responders must immediately locate and access disconnects—visibility and accessibility are life-safety requirements, not just code technicalities. Document location on as-built drawings and provide location diagram to fire department.

Can I use the same disconnect for DC and AC circuits?

No—DC and AC disconnects are fundamentally different technologies. DC disconnects require: extended contact gaps (2-3× longer than AC), magnetic blowout arc chutes, double-break contacts for >1000V systems, arc-resistant materials. AC disconnects rely on natural current zero-crossings for arc extinction (100-120 times/second); DC has no zero-crossings so arcs sustain indefinitely without specialized interruption. A 240V AC rated disconnect typically handles only 60-125V DC due to sustained arc challenge. Using AC disconnect for DC solar creates catastrophic failure risk: arc may weld contacts closed (cannot turn off), explode enclosure, ignite fire. NEC 690.17 requires disconnect rated for DC voltage ≥ system V_oc. Always verify DC voltage rating marked on disconnect nameplate. Hybrid AC/DC rated switches exist but are rare and expensive—typically use separate dedicated DC disconnect for solar and separate AC disconnect for inverter output.

How do I know if my disconnect is properly grounded?

Verify proper grounding with four-step test: (1) Visual: Equipment grounding conductor (EGC) connected to ground terminal inside disconnect, proper size per NEC 250.122 (6 AWG copper for 200A disconnect); (2) Bonding: Disconnect enclosure bonded to ground terminal via bonding screw or jumper; (3) Continuity: Measure resistance from enclosure to ground terminal, should read <0.1Ω; (4) Ground fault path: Use ground tester or momentarily short line conductor to enclosure through known resistor, measure voltage rise on enclosure (should be <50V for adequate ground). Grounding electrode connection required if PV system at separate building or >50 feet from main service—test ground rod resistance with dedicated ground tester, target <25Ω per NEC 250.53. Common failures: EGC too small, missing bonding screw, corroded connections, aluminum conductors not treated with anti-oxidant compound. Re-check grounding annually during maintenance inspections.

What torque specification should I use for disconnect terminals?

Torque depends on terminal size and type—ALWAYS consult manufacturer datasheet for exact specification. Typical ranges: Small screw terminals (14-10 AWG) = 20-30 lb-in (2.3-3.4 Nm); Medium lug terminals (8-2 AWG) = 35-50 lb-in (4.0-5.6 Nm); Large lug terminals (1/0-250 kcmil) = 50-75 lb-in (5.6-8.5 Nm); Bus bar studs (300-750 kcmil) = 75-150 lb-in (8.5-17 Nm). Use calibrated torque wrench or torque screwdriver—set to specified value, tighten until tool clicks or releases, STOP immediately (do not continue turning after click). Re-torque after 10-15 minutes as terminals “settle”. Under-torque causes 60% of connection failures through high-resistance heating; over-torque causes 10% through stripped threads and crushed terminals. Field shortcut: “firm hand-tight” ≈ 25-30 lb-in but this is emergency-only technique—always use calibrated tools for initial installation and maintenance. Mark torqued connections with paint dot to show work completed.

How do I test a DC disconnect switch before energizing the system?

Follow four-test sequence: (1) Visual inspection—all terminals torqued, no exposed conductors, labels installed, enclosure sealed, disconnect operates smoothly; (2) Continuity test—disconnect CLOSED, measure LINE to LOAD resistance both polarities, should read <0.01Ω; (3) Insulation resistance—disconnect OPEN, apply 500V DC test for 1 minute using megohmmeter, test LINE-to-ground >1MΩ, LOAD-to-ground >1MΩ, LINE-to-LOAD >10MΩ; (4) Polarity verification—energize array, measure LINE side voltages, verify positive terminal shows +V_oc, negative shows -V_oc or 0V depending on grounding. After energization: voltage verification (LOAD voltage should equal LINE with <2% drop), thermal inspection after 30 minutes operation (no terminal >30°C above ambient), operational cycling (open/close 3-5 times, verify visible break and voltage drops to 0V when open). Document all test results with date, technician name, and measured values. Failing any test requires investigation and correction before proceeding—never energize system with failed pre-energization tests.

What labels are required on a solar DC disconnect by code?

NEC 690.56 requires permanent label on disconnect reading “PHOTOVOLTAIC SYSTEM DISCONNECT” plus: nominal voltage (e.g., 800V DC), maximum voltage (e.g., 920V DC at coldest temp), short-circuit current (e.g., 88A), available fault current (e.g., 180A), date of calculation. Additional required markings: arc flash warning per NFPA 70E with PPE category and incident energy, directional labels (LINE/LOAD or INPUT/OUTPUT with polarity +/-), operating instructions if not obvious, rapid shutdown notation if applicable (NEC 690.12). Label specifications: reflective weather-resistant UV-stable material, black text on yellow background (ANSI Z535.4), minimum 3/8″ text height for primary words, permanently affixed via adhesive or mechanical fasteners. Manufacturer data plate must remain visible showing DC voltage rating, current rating, UL listing. Handwritten labels insufficient—use professional pre-printed labels or label maker. Missing or incorrect labels cause inspection failures and create safety hazards for maintenance personnel and emergency responders who need immediate hazard identification.

결론

DC 차단 스위치 professional installation requires systematic attention to NEC location requirements, proper wire sizing accounting for temperature derating, precise terminal torque application, comprehensive grounding and bonding, code-compliant labeling, and thorough pre-energization testing. Unlike routine AC electrical work, DC disconnect installation involves life-safety implications where errors create sustained arc hazards, shock risks during maintenance, and inspection failures delaying project commissioning.

Critical Installation Success Factors:

Location and Accessibility: NEC 690.13 “readily accessible” requirement is non-negotiable—mounting height 3.5-6.5 feet, 3-foot clear working space, no ladders required, not behind locked doors. Building disconnect at service entrance point, equipment disconnect within sight of inverter (50 feet AND visible) OR remote lockable. Emergency responders must immediately locate and access disconnects—poor location defeats safety purpose regardless of perfect electrical work.

Wire Sizing Methodology: Calculate from SOURCE current (I_sc × 1.56) with temperature derating applied BEFORE selecting conductor size. Common failure: sizing wire to match disconnect rating while ignoring 60°C rooftop ambient reduces ampacity 40%, creating severe undersizing. Always determine installation environment temperature and apply NEC Table 310.15(B)(2)(a) correction factors. Under-sized conductors overheat before disconnect operates—defeating protection purpose.

Terminal Torque Precision: Use calibrated torque wrenches per manufacturer specifications (typically 35-75 lb-in for main terminals). Under-torque causes 60% of connection failures through high-resistance heating; over-torque strips threads and crushes terminals. Re-torque after 10-15 minutes as terminals settle. Never use impact drivers on electrical terminals—precise torque application non-negotiable for 25-30 year reliable operation.

Grounding and Bonding: Size equipment grounding conductor per NEC Table 250.122 based on overcurrent device rating (NOT conductor size)—6 AWG copper minimum for 200A disconnect. Bond enclosure to ground terminal, verify continuity <0.1Ω. Grounding electrode system required for remote installations—test ground rod resistance <25Ω per NEC 250.53. Proper grounding ensures ground fault current path integrity protecting personnel from touch potentials during faults. Labeling and Testing: Install permanent weatherproof labels with complete system data per NEC 690.56. Execute four-test pre-energization sequence: visual inspection, continuity (verify <0.01Ω closed), insulation resistance (verify >1MΩ to ground), polarity verification. After energization: thermal inspection confirms no hot spots >30°C rise. Documentation of test results and as-built photos essential for maintenance and troubleshooting throughout system lifespan.

For solar installation contractors and electrical professionals, proper DC disconnect installation represents fundamental safety infrastructure enabling personnel protection during maintenance operations. First-time-right installation passing inspection and operating reliably requires understanding DC-specific challenges, following systematic procedures, and maintaining quality standards throughout 25-30 year project lifecycles.

Related Installation Resources:
Solar Disconnect Fundamentals – Product technology basics
DC Circuit Breaker Installation – Overcurrent protection procedures
PV Combiner Box Wiring – System integration practices

Installation Support: SYNODE provides field installation training, quality verification audits, and commissioning assistance for solar electrical contractors. Contact our field services team for on-site support, troubleshooting consultation, and NEC compliance verification.

마지막 업데이트: 2025년 10월
작성자: SYNODE Field Installation Team
Technical Review: Master Electricians, NABCEP Installation Specialists
Code References: NEC Article 690:2023, NEC Article 250:2023, NFPA 70E:2024

사랑을 나누세요
krad
krad

krad는 태양광 DC 보호 시스템에 대한 깊은 전문성을 갖춘 SYNODE의 기술 콘텐츠 전문가입니다. 재생 에너지 분야에서 10년 이상의 경험을 쌓은 그는 북미, 유럽 및 아시아 전역의 300개 이상의 상업용 태양광 프로젝트에 기술 지침을 제공했습니다. 그의 업무는 회로 보호 설계, 서지 보호 구현 및 태양광 설비의 전기 규정 준수에 중점을 두고 있습니다. krad는 태양광 시스템 설계 자격증을 보유하고 있으며 전기 엔지니어와 정기적으로 협력하여 게시된 모든 콘텐츠가 IEC, UL 및 NEC 표준을 충족하는지 확인합니다.

기사 : 45